What you need to say is the whole process of building construction, and the target is the unit project, but each unit project is different, its structure and decorative lamp design industry is different, and the construction sequence is also different. Let's take a civil high-rise residential building as an example
The overall division order is first structure, then decoration, and water and electricity interspersed construction. Specifically, it is.
1. Reinforced concrete cast-in-place pile foundation construction;
2. Earthwork excavation;
3. Basement construction;
4. Construction of the main structure of the upper part;
5. Roofing and waterproofing construction;
6. Exterior wall decoration construction;
7. Interior decoration construction, including ceiling, wall and ground (can be synchronized with exterior decoration);
8 Outdoor loose water, steps, etc.
9. Hydropower installation (in the construction of the structure, it is mainly the embedded pipe box box, and the corresponding system is installed in the decoration synchronization).
Looking at the construction schedule of the unit project in detail, it is very clear.
-
You're talking about large districts! The process is far more complicated than you said, the water supply and drainage are buried, the network power supply is buried, and the doors and windows are completed after the masonry, so that the ash can be touched in place at one time. There are a lot of things that depend on the situation, and that's all you said.
-
Positioning and pay-off, earthwork excavation, site leveling, elevation determination, cushion, reinforcement engineering, template engineering, foundation acceptance, earthwork backfilling, reinforcement engineering of the main part, template engineering, kiln engineering, masonry engineering of the filling wall, main body acceptance, decoration engineering (including the interior and exterior wall plastering, external wall insulation, etc.), and some projects are carried out synchronously, there is no so-called sequence, as long as it does not affect the construction and requirements of the project.
-
Summary. Dear, <>
Hello, glad to answer for you. The general process of construction engineering can be divided into the following stages: 1. Civil engineering stage:
The civil engineering stage is the first stage of construction engineering, including foundation engineering, foundation engineering, main structure engineering, etc. The main processes include geological exploration, foundation treatment, foundation pit excavation, formwork engineering, reinforcement engineering, concrete pouring, structural waterproofing, etc. 2. Installation stage:
The installation stage is the second stage of construction engineering, which mainly refers to the installation of building equipment. The main processes include electrical installation, pipeline installation, air conditioning installation, fire protection installation, etc. 3. Decoration stage:
The renovation stage is the third stage of the construction project, which mainly refers to the renovation work inside the building. The main processes include bricklayer works, carpentry works, painting works, hydropower works, etc. 4. Completion stage:
The completion stage is the last stage of the construction project, which mainly refers to the acceptance, delivery, warranty and other work of the building. The main processes include acceptance, delivery, warranty, etc.
General process of construction works.
That's it, and then what are the processes.
Dear, <>
Hello, glad to answer for you. The general process of construction engineering can be divided into the following stages: 1. Civil engineering stage:
The civil engineering stage is the first stage of construction engineering, including foundation engineering, foundation engineering, main structure engineering, etc. The main processes include geological exploration, foundation treatment, foundation pit excavation, formwork engineering, reinforcement engineering, concrete pouring, structural waterproofing, etc. 2. Installation stage:
The installation stage is the second stage of construction engineering, which mainly refers to the installation of building equipment. The main processes include electrical installation, pipeline installation, air conditioning installation, fire protection installation, etc. 3. Decoration stage:
The renovation stage is the third stage of the construction project, which mainly refers to the renovation work inside the building. The main processes include bricklayer works, carpentry works, painting works, hydropower works, etc. 4. Completion stage:
The completion stage is the last stage of the construction project, which mainly refers to the acceptance, delivery, warranty and other work of the building. The main processes include acceptance, delivery, warranty, etc.
Dear, it's the installation stage, you can follow the steps above.
How to write it, can you elaborate on it? Behind is the raft foundation or something.
Pro, structural waterproofing, electrical installation, pipeline installation, air conditioning installation, fire protection installation, bricklayer engineering, carpentry engineering, painting engineering, hydropower engineering, acceptance, delivery, warranty.
How to write the above, pro, you can go on directly, or if you can change it, you can follow the following order: foundation engineering, foundation engineering, main structure engineering, geological exploration, foundation treatment, foundation pit excavation, formwork engineering, reinforcement engineering, concrete pouring, structural waterproofing, electrical installation, pipeline installation, air conditioning installation, fire installation, bricklayer engineering, carpentry engineering, painting engineering, hydropower engineering, acceptance, delivery, warranty.
If you can't change it, follow this order: structural waterproofing, electrical installation, pipeline installation, air conditioning installation, fire protection installation, bricklayer engineering, carpentry engineering, painting engineering, hydropower engineering, acceptance, delivery, and warranty.
-
The general flow of the civil construction process is as follows:
1. Measuring the line of defense;
2. Excavation foundation pit;
3. copying flat; 4. Make concrete foundation cushion;
5. Binding steel bars, formwork installation, and pouring concrete;
6. Measurement pay-off (axis, column positioning);
7. Column reinforcement binding, formwork installation, concrete pouring;
8. Beams and slabs are tied with steel bars, formwork is installed, and concrete is poured, which is carried out in turn until the capping.
9. Masonry construction, interior and exterior wall plastering, door and window frame installation, roof waterproofing, exterior wall finishing construction, etc., which can be interspersed with construction after the main structure is partially completed.
-
Construction sequence: foundation construction: leveling the site - positioning and pay-off - foundation trench excavation - installation of cushion template - laying cushion - binding foundation reinforcement - installation of foundation template - pouring concrete foundation - masonry foundation - binding JQL steel bar - installation of JQL template - pouring JQL concrete - backfill earthwork main construction:
According to each layer) binding GZ steel bar - masonry masonry - installation column, beam, plate formwork - binding beam, steel plate - pouring beam plate concrete, each layer of the same process. Roof construction: laying insulation - laying screed - laying waterproof layer.
Decoration works: (from top to bottom) interior and exterior wall plastering - floor cleaning - pouring cushion - laying floor floor - indoor and outdoor painting.
-
1. Project proposal.
2. Feasibility study report.
3. Preliminary design.
4. Construction drawing design.
5. Annual investment plan.
6. Commencement report.
7. Completion acceptance.
2. Construction engineering refers to the engineering entity formed through the construction of various types of housing buildings and their ancillary facilities and the installation of supporting lines, pipelines and equipment. among others"Housing construction"It refers to the project with roof, beams, columns, walls, foundations and internal spaces that can form an internal space to meet the needs of people's production, residence, study and public activities.
-
At the time of bidding, it is already the construction cycle, and the construction project starts from the beginning of the project, planning and land acquisition, architectural design, bidding construction, etc.
-
Construction contents-||According to the construction process, the first step, the second step, the third step. Briefly describe the whole process of construction, dear, hello, I am happy to answer your questions, the whole process of construction includes the following steps: Step 1:
Preparation Before construction, a series of preparations need to be carried out, including determining the construction plan, formulating the construction plan, preparing construction materials and equipment, organizing construction personnel, etc. Step 2: Foundation construction Foundation construction is the first step of building construction, including foundation excavation, foundation pouring, underground pipeline laying and other work.
Step 3: Main body construction The main body construction is the core part of building construction, including wall masonry, beam and column construction, roof construction, door and window installation, etc. Step 4:
Decoration construction Decoration construction is the last step of building construction, including interior decoration, exterior wall decoration, road greening and other work. The above is the process of building construction, and the specific construction content will vary according to different projects and engineering needs.
-
According to the construction steps:
Foundation Main Body Roofing Interior Decoration Indoor Equipment Plumbing:
1. Foundations and foundations. Excavation of foundation pit (foundation groove) to do foundation backfilling.
2. Main structure. It depends on what is the structural form, brick-concrete, reinforced concrete, steel structure, etc., brick-concrete structure: brick-laying pouring structural columns, ring beams, cast-in-place (prefabricated) roofs;
Reinforced concrete is simple: binding steel bars (columns, beam plates) supporting formwork (columns, beam plates) pouring concrete filling walls;
Steel structure: processing, installation of steel columns, processing, installation of steel beams, steel frame roof panels.
3. Roofing. It is divided into rigid and flexible roofs, and cement mortar and concrete belong to rigid roofs; Membranes, waterproof coatings, etc. belong to flexible roofing.
4. Decoration and decoration. It is divided into several parts: ground, wall, door and window installation, etc.
5. Equipment pipelines include: installation of cables, wires, lamps and lanterns; plumbing appliances for water supply and drainage; installation of ventilation and air conditioning equipment and pipes; Heating; firefighting, etc.
Tender Template (Construction Works).
Construction unit: >>>More
I'm studying civil engineering, I'll be honest with you, don't study, it's a popular major for men to study civil engineering, but women tend to prefer their grades in our school, but it's hard to find a job. Because the construction company does not believe in girls. Because they think that girls are afraid of hardship, and it is not easy to manage (dormitories, toilets have to be rearranged for you), you can only go to some units such as design institutes, but there are very few places. >>>More
Filing and registration form of construction project completion statement. >>>More
Traditional engineering insurance includes construction engineering insurance and installation engineering insurance, but with the development of various scientific and technological projects, scientific and technological engineering insurance has also become an important part of engineering insurance. >>>More
1. Construction drawings and design change records.
2. The main equipment and materials certificate, the re-inspection report and the equipment schedule 3, and the acceptance record of the concealed project. >>>More