-
Team A can complete 1 123 days a day Team A completes 3 1 12 1 1 4 every day
Team A does 3 days and then Team B does 2 days, which is exactly half done.
So team B does 2 days to complete 1 2-1 4 1 4
So Team B completes 1 4 2 1 8 every day
Teams A and B cooperate to complete 1 12 + 1 8 5 24 every day, and after doing it, it is found that the two periods of time are equal.
So share 1 (1 8 + 5 24) 2 6 days.
-
A does it alone, does 1 12 a day, B does it alone, does 1 9 a day, and A does it for x days first.
1/12)x+(1/9)*(10-x)=11/12)x+10/9-(1/9)x=1
1/9=(1/9-1/12)x
1/9=(1/36)x
4=xx=4
A did it for 4 days.
-
The ergonomics of B are:
Set up for x days.
1/12+1/8)*x/2+1/8*x/2=15/48*x+1/16*x=1
It took 6 days to solve x=6 answers.
-
Set two periods of time for x days.
1/12+1/8)x+1/8x=1
x=3 for 3+3=6 days.
-
Shared 8 days.
Just figure out how many days Team B will use.
It's simple.
-
Team A can complete it in 12 days alone.
Team A completes 1 12 per day
3 days to complete 3 1 12 1 4
After team A does 3 days, team B does 2 days, which is exactly half done.
So team B does 2 days to complete 1 slip and 2-1 4 1 4, so team B completes 1 4 2 1 8 every day
The two teams A and B are cautious and cautious every day, and after completing 1 12 + 1 8 5 24 every day, they find that the two periods of time are equal.
So. Shared 1 (1 8+5 24) 2 6 days.
-
Assuming that all 10 days are dry, the project should be completed.
1/9 10 10/9
More than it actually is.
1 out of 9 1 out of 9 1 out of 9 1 out of 1 9 out of 1 9 1 out of 1 9 1 1 1 1
B completes the work more every day than A.
1/9 1/12 1/36
A worked. 1/9 1/36 4 days.
B worked. 10 4 wheels sedan orange 6 days.
-
He's right, right answer, you're wrong, I feel like you're just thinking too much, what, B, according to A's standards... Don't think too much about it, just let them do it.
Suppose the entire engineering quantity is 1
A can dry 1 20= per day
B can dry 1 10 = per day
If A and B take turns to do it, they will work together every two days.
It will be completed in 12 days.
There is still 1 day left, and the first is done.
For the rest, B dry for half a day.
The total number of days is 12+1+.
-
When the master completed 40 of his tasks, the apprentice processed 240. Then when the master completes 100%, the apprentice has processed 240*100% 40%=600 At this time, the apprentice is still 20 short of completion, that is to say, the apprentice is 80% complete, then the apprentice has completed a total of 600 80%=750 This batch of parts has 750*2=1500.
-
This batch of parts is 1500 pieces, and this problem can be calculated without equations, with proportions. First, calculate the velocity ratio of the teacher:apprentice, and then the root velocity ratio can be calculated.
-
The speed ratio of master to apprentice is 1
When the master completes 40%, the apprentice completes 40%.
240 32% = 750 * 2 = 1500 pcs.
It's a very simple question.
-
Solution: 1-1 5-1 2) (1 5-1 7)=21 4 hours).
A: One more hour.
-
Set the apprentice to do x in an hour, and the master to do y in an hour. There are 30x parts in total.
The two of them processed 1 of the 3 parts of this batch in 4 hours. Rule.
4(x+y)=1/3*30x.3x=2y, and 2 3*30x=20x remains
The rest of the master does it, that is, 20x y = 20x (3x 2) = 40 3 hours.
-
It takes 30 hours for the apprentice to do it alone: the apprentice's efficiency is 1 30 of the total amount of completion per hour, and the master-apprentice cooperates for 4 hours to process 1 3 of the batch of parts: the master-apprentice cooperation processes 1 3 4 = 1 12,; The master completes 1 12-1 30 = 1 20 per hour
The rest is done by the master alone: the remaining 1-1 3=2 3;The master does 2 3 1 20 = 40 3 = 13 hours and 20 minutes.
Integer: (1-1 3) (1 3 4-1 30) = 13 hours and 20 minutes Answer: omitted.
-
Suppose that a batch of workpieces is "1" and the processing speed of the master is x, then 4(x+1 30)=1 3
The solution is x=1 20
-
Solution: Assuming that the specified date is x days, then:
A ergonomics: 1 x
B efficiency: 1 (x+4).
According to the title, it gets: 3 x+x (x+4)=1
3(x+4)+x^2=x(x+4)
3x+12+x^2=x^2+4x
x = 12, i.e. the specified date is 12 days.
Refer to the upstairs, but upstairs doesn't know then without adding a statement? >>>More
Combine the two formulas and get it.
k/x=-x-6 >>>More
Freezing three feet, not a day's cold. Learning is a gradual process, and it is not possible to "make leaps and bounds". It is necessary to study hard and accumulate slowly, so that quantitative changes can cause qualitative changes. >>>More
Categorize 1 to 50 and divide them into 7 divided by 7 and divisible by 7, with 8 remaining 1 and 1 remaining and 7 others. In the same way, the elements of the remaining 2 and the remaining 5 cannot exist at the same time, the remaining 3 and the remaining 4 cannot exist at the same time, and the divisible can only exist in one element at most, so at most there are 8 remaining 1, the remaining 2 or 5 choose one category, the remaining 3 or 4 choose one category, and the divisible one can be selected, a total of 23.
There are many ways to install WindowsXP, and there are usually the following situations: >>>More