What are the contents of the qualification of railway construction engineering construction enterpri

Updated on society 2024-03-18
3 answers
  1. Anonymous users2024-02-06

    The first-class qualification units for railway construction general contracting include East China Construction Project, China Railway Bridge Project, and China Railway Tenth Bureau, as follows:

    1. According to the query of relevant information, it can be seen that East China Construction Engineering has the special qualification for general contracting of railway and highway engineering construction, and is engaged in railway track laying and girder, bridges, tunnels and other pavement projects.

    2. Haitie Xunzhi Road and Bridge Project has the first-class qualification for general contracting of railway engineering construction, and has the first-class qualification for general contracting of national municipal engineering construction.

    3. China Railway Tenth Bureau is mainly engaged in general contracting of construction projects, has the first-class qualification of general contracting of railway construction, and is engaged in projects such as railway steel structure inspection and elimination, railway electrical affairs, and electrification engineering.

  2. Anonymous users2024-02-05

    The qualifications related to railways include: general contracting qualification for railway engineering construction, professional contracting qualification for railway electrical engineering, professional contracting qualification for railway track laying and girder engineering, and professional contracting qualification for railway electrification engineering.

  3. Anonymous users2024-02-04

    Level 1 qualification standards

    Enterprise assets: net assets of more than 100 million yuan.

    Key personnel of the enterprise:

    1) There are no less than 15 first-class registered constructors in railway engineering.

    2) The technical person in charge has more than 10 years of experience in railway engineering construction technology management, and has a senior professional title in railway engineering (or bridge engineering or tunnel engineering); There are no less than 75 personnel with intermediate or above professional titles in railway engineering related majors.

    3) There are no less than 50 construction site management personnel with post certificates, and the construction personnel, surveyors, quality personnel, safety officers, testers, material personnel, standard personnel, mechanics, labor personnel, and data personnel are complete.

    4) There are no less than 200 skilled workers above the intermediate level who have passed the assessment or training.

    Enterprise engineering performance:

    In the past 10 years, he has undertaken the construction of 3 of the following 5 categories, of which at least the projects listed in Category 1 are of acceptable quality.

    1) A total of more than 150 kilometers of railway comprehensive projects (excluding railway electrical, electrification and track-laying and girder projects);

    2) 2 railway tunnels with a total length of more than 1,000 meters;

    3) 3 railway bridges with a single span of 32 meters and a bridge length of more than 100 meters;

    4) 2 new or renovated stations with a single contract value of more than 50 million yuan;

    5) 2 general contracted railway comprehensive projects with a single contract value of more than 100 million yuan (excluding railway electrical, electrification and track-laying and girder projects).

Related questions
9 answers2024-03-18

The main terms of the construction contract, also known as the construction and installation contract, are: (1) the name and location of the construction project; (2) the scope and content of the construction project; (3) The date of commencement and completion of the construction of the construction project and the date of commencement and completion of the intermediate delivery project; (4) The quality warranty period and warranty conditions of the construction project of the construction project; (5) the cost of the construction project; (6) Methods for payment, settlement and acceptance of the construction price of construction projects; (7) The date on which the construction design documents and estimates, budgets and technical data of the construction projects are provided; (8) Construction materials and equipment for construction projects and the deadline for entering the site; (9) Matters of mutual cooperation between the two parties; (10) Liability for breach of contract in the construction of construction projects.

2 answers2024-03-18

Although the labor subcontract is simpler than the construction contract, it has some peculiarities. It should be noted that, according to the content of the model "Subject or Benchmark of Labor Subcontract for Construction Projects" issued by the Ministry of Construction and the State Administration for Industry and Commerce in August 2003, combined with the specific contract of the construction contract signed between the contractor and the owner, the main contents of the labor subcontract are: (1) The qualification of the labor subcontractor. >>>More

7 answers2024-03-18

In the case of a part-time construction site, it is generally charged according to the completed area, and the specific amount of money per square depends on the area.

6 answers2024-03-18

First, first enter the venue to prepare:

1. Project commencement report, construction permit, construction organization design, materials and equipment for review. >>>More

6 answers2024-03-18

Approval by the construction department and the communications management department.