Package pillar construction process

Updated on society 2024-08-01
3 answers
  1. Anonymous users2024-02-15

    The construction process of the column is as follows:

    1) Preparation for construction.

    1. Personnel preparation: 2 installers, 2 porters, 1 welder.

    2. Tool preparation: 1 electric hammer, 1 iron hammer, 2 movable and fixed wrenches, 1 2-meter ruler, 1 hanging hammer, 2 angle rulers, 1 wire brush, 2 hand electric drills, 2 vigorous pliers, 2 "+ word screwdrivers, 1 glue gun, 1 gray knife, 1 tape measure, 2 red and blue pencils, 1 set of welding machine, 1 level.

    2) Construction pay-off.

    1. The verticality of the structural column is correct, and the vertical line of the axis of the keel installation position is measured with an angle ruler, and the data is recorded, and the average value is magnified by 10 mm.

    2. Mark the position of the axis with a red and blue pencil on the floor, draw it out with a 90° extension line of the angle ruler, determine the axis of the keel at the relative position, and the correct error is the same as above.

    3) Upright installation.

    1. Connecting the corner code plus anticorrosive glue type plus square gasket, plus spring washer, plus pair bolt and keel hand screwing fixation.

    2. Dock the upper mouth of the keel to identify the position, and temporarily fix the spot welding corner code.

    3. The vertical error of the keel with a 2-meter ruler is 2 mm, until the three-dimensional adjustment.

    4. Review the diameter and compare it according to the pay-off method.

    5. The contact position between the full welding corner code and the embedded parts requires a welding height of 6-8 mm, smooth lines, and no bubbles and slag inclusions are allowed.

    6. Slag removal and rust removal, and two anti-rust paint coatings.

    4) Beam installation.

    1. Draw the axis of the beam position according to the construction drawings.

    2. Weld and fix the corner code according to the identification line.

    3. Place the beam between the two corners of the yard, and fine-tune it to the level of the entry and exit position and the surface of the erection.

    4. Correct levelness and entry and exit position.

    5. Full welding. 6. Slag removal and rust removal, and two anti-rust paint coatings.

    5) Hanging board. Identify the central axis of the vertical and beam with the principle of horizontal and vertical, adjust the arc plate according to the design glue seam, wrap the entire unit column, and then make the overall correction to ensure that the upper and lower grid, vertical and flatness error is 2 mm, and all the screws are completed.

    6) Gluing and cleaning.

    1. Tear the folded part of the protective film of the aluminum honeycomb panel, and paste the masking paper at the fold at the 90° corner. The masking paper should be folded into a 90° corner at the glue seam of the "+", and the entire plate of masking paper should be in place at one time, and swept it hard to avoid wrinkles in the masking paper.

    2. Stuff foam round beech, which is required to be dense and straight.

    3. When pouring glue, go in a straight line, from top to bottom, from left to right, and finish it at one time.

    4. The squeegee should also be used to the end at one time according to the principle of glue injection, and the scraping speed at the "+" interface is slightly slower.

    5. Tear off the masking paper, pull it at an angle of 45° outward, and concentrate the torn masking paper into the trash can to avoid environmental pollution.

    6. After the weather-resistant glue is dried, tear off the outer protective film when sweeping the tail, and wipe off the surrounding dust with a dry rag.

  2. Anonymous users2024-02-14

    What kind of bag do you use? Stone, tile, sheet metal, wood veneer, leather (fabric) upholstered ......, to make it clear wow, otherwise how to tell you.

  3. Anonymous users2024-02-13

    <> is divided into five steps. The first step is to prepare for the work, and the preparation of personnel and tools is crucial. The second step is the preparation for the implementation of the project, the marks that should be made at each location should be noted, and the data that needs to be accurately calculated should also be determined.

    The third step is the installation work, which needs to be reinforced according to the previous markings corresponding to the installed parts. The fourth step is the installation of the beams and hanging plates, which can only be carried out according to the previous accurate calculations. The last step is to reinforce and clean up each part, and after checking that it is correct, you need to tear off the protective film to sell the mold, and then wipe the dust.

Related questions
5 answers2024-08-01

1) Varnish construction process.

Clean the surface of the wood Finish with sandpaper Finish on the powder Sandpaper Scrape the first putty, sandpaper polish Scrape the putty for the second time, polish the fine sandpaper Brush the oil Brush the first varnish Spell the color, refill the putty, polish the fine sandpaper Brush the second varnish, fine sandpaper polish Brush the third varnish, polish the water sandpaper sandpaper, wax, polish. >>>More

10 answers2024-08-01

The general order of brick wall masonry is to copy the flat, pay off, place the bricks, stand the number of leather rods, plate corners, hang the line, masonry, hook joints, and clean.

5 answers2024-08-01

Do the math how much it will cost you to renovate your home >>>More

8 answers2024-08-01

Soundproofing paint is used to decorate walls not only for aesthetics, but also for its high safety. Nowadays, many homes use soundproof paints to create a quiet and comfortable living environment. So what is the construction process of sound insulation coatings? >>>More

5 answers2024-08-01

Do the math how much it will cost you to renovate your home >>>More