-
1. Procurement can be carried out in accordance with competitive negotiation.
According to Article 30 of the ** Procurement Law of the People's Republic of China, goods or services that meet one of the following circumstances may be procured through competitive negotiation in accordance with this Law:
A) after the bidding there is no ** bidding or no qualified bidding or re-bidding failed to establish;
2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined;
C) the time required to adopt the bidding can not meet the urgent needs of users;
4) The total amount cannot be calculated in advance. ”
2. Competitive negotiation, inquiry or a single way of procurement.
According to the "Measures for the Administration of Non-bidding Procurement Methods for Procurement", Article 27 Procurement projects that meet one of the following circumstances may be procured through competitive negotiation:
After the bidding, there is no first-class bidding or no qualified bid, or the re-bidding is not established;
The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined;
The total amount cannot be calculated in advance due to reasons such as the time and quantity of art procurement, patents, know-how or services cannot be determined in advance.
The above information ** real-time bidding network.
-
After the original examination and approval, the approval department may not be invited to bid.
According to Article 38 of the Measures for Bidding and Bidding for the Construction of Engineering Construction Projects, the bidder shall deliver the bidding documents to the bidding place in a sealed manner before the deadline for submitting the bidding documents required by the bidding documents. After the tenderer receives the bidding documents, it shall be issued to the bidder to indicate the signatory and the time of receipt of the voucher, before the bid opening any unit or individual shall not open the bidding documents.
The tender documents delivered after the deadline for submission of bidding documents required in the bidding documents, the tenderer shall refuse to accept them.
If there are less than three bidders who submit bidding documents for projects that must be tendered in accordance with the law, the tenderer shall re-bid in accordance with the law after analyzing the reasons for the failure of the bidding and taking corresponding measures. If there are still less than three bidders after the re-bidding and burial, it is a construction project that must be examined and approved, and the bidding can no longer be carried out after the original examination and approval and approval department examination and approval; For other engineering construction projects, the tenderer may decide not to bid for other projects at its own discretion.
-
According to the ** Procurement Law of the People's Republic of China, "Article 30 Competitive negotiation may be used in accordance with this Law for goods or services that meet any of the following circumstances.
Method procurement: (1) After the bidding, there is no first-class bidding or no qualified bidding or the re-bidding is not established; 2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined; C) the time required to adopt the bidding can not meet the urgent needs of users; 4) The total amount cannot be calculated in advance. ”
Extended Materials. 1.Bidding and bidding.
is in a market economy.
It is a transaction method used when buying and selling bulk goods, awarding and contracting engineering construction projects, and purchasing and providing service projects. In this transaction mode, the purchaser of the project procurement (including the purchase of goods, the contracting of the project and the procurement of services) is usually the tendering party, through the issuance of a tender announcement or to a certain number of specific contractors and contractors.
Invitation to tender is issued.
and other ways to issue bidding and procurement information, put forward the nature of the required procurement project and its quantity, quality, old technical requirements, delivery date, completion period or time to provide services, as well as other bidding and procurement conditions such as the qualification requirements of contractors and contractors, indicating that they will choose the best to meet the procurement requirements of the contractor and the contractor to sign a chain of procurement contract intentions, by each intention to provide the procurement of goods, projects or services and other conditions in response to the bidding requirements, to participate in the bidding competition. After the tenderer reviews and compares the bidders' ** and other conditions, the winning bidder is selected and signed a procurement contract with it.
2.Bidding is also referred to as bidding. Bidding and bidding is an act of commodity trading, two aspects of the transaction process. Tendering and bidding is an international practice and a commodity economy.
The product of a high degree of development is an organized way of selecting the best by applying the methods of technology and economy and the role of the competition mechanism of the market economy. This method is in the procurement of goods, projects and services, the tenderer through the pre-announced procurement and requirements, attract a large number of bidders in accordance with the same conditions for equal competition, in accordance with the prescribed procedures and organize technical, economic and legal experts to conduct a comprehensive review of many bidders, from which the selection of the winning bidder of the project behavior process. Its essence is to obtain the best goods, works and services at a low level.
-
Legal analysis: After three failed bidding bids for government procurement, you can apply to change the procurement method and choose competitive negotiation, inquiry procurement, single procurement or other procurement methods identified *****by the procurement supervision and management department. The validity period of the bid is generally in the instructions to bidders in the bidding documents, which will clearly require the validity period of the bid for how many days.
Legal basis: Article 30 of the ** Procurement Law of the People's Republic of China, goods or services that meet one of the following circumstances may be procured through competitive negotiation in accordance with this law: (1) There is no ** commercial bid or no qualified subject matter after the bidding, or the re-bidding fails to be established; 2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined; C) the time required to adopt the bidding can not meet the urgent needs of users; 4) The total amount cannot be calculated in advance.
-
Analysis of the old town of the law:
1.What to do after two failed tenders.
2.Procurement can be carried out on a competitive basis.
3.It can be procured by competitive negotiation, inquiry or a single ** method.
Legal basis: Procurement Law of the People's Republic of China on Lead** Article 30 Goods or services that meet any of the following circumstances may be procured through competitive negotiation in accordance with this Law:
A) after the bidding there is no ** bidding or no qualified bidding or re-bidding failed to establish;
2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined;
C) the time required for the use of Qingrough bidding can not meet the urgent needs of users;
4) The total amount cannot be calculated in advance.
-
What to do after two failed tenders.
1. Procurement can be carried out in accordance with competitive negotiation.
According to Article 30 of the ** Procurement Law of the People's Republic of China, goods or services that meet one of the following circumstances may be procured through competitive negotiation in accordance with this Law:
A) after the bidding there is no ** bidding or no qualified bidding or re-bidding failed to establish;
2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined;
C) the time required to adopt the bidding can not meet the urgent needs of users;
4) The total amount cannot be calculated in advance. ”
2. Competitive negotiation, inquiry or a single way of procurement.
According to the "Measures for the Administration of Non-bidding Procurement Methods for Procurement", Article 27 Procurement projects that meet one of the following circumstances may be procured through competitive negotiation:
A) after the bidding there is no ** bidding or no qualified bidding or re-bidding failed to establish;
2) The technology is complex or special in nature, and it is not possible to determine the detailed specifications or specific requirements;
3) The time required for the use of bidding cannot meet the urgent needs of users due to reasons that are not foreseeable by the procurer or delayed by the non-procurer;
4) The total amount cannot be calculated in advance due to reasons such as the time and quantity of art procurement, patents, know-how or services cannot be determined in advance.
In practice, we need to know how to deal with the failure of the bidding, so as to better complete the bidding of the project, which is also the content that enterprises need to understand clearly, in order to regret the high to solve.
-
<> after a failure in a bidding, the bidding purchaser can conduct a second bidding, but occasionally there will be two failures in the bidding, so how to deal with the failure of the two bidding? Let's take a look!
1. According to the ** Procurement Law of the People's Republic of China, "Article 30 Goods or services that meet one of the following circumstances may be procured through competitive negotiation in accordance with this Law:
A) after the bidding, there is no ** travel business bidding or there is no qualified subject or the re-bidding is not established;
2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined;
C) the time required to adopt the bidding can not meet the urgent needs of users;
4) The total amount cannot be calculated in advance. "Procurement can therefore be carried out on the basis of competitive negotiations.
2. According to the "Administrative Measures for Bidding and Bidding for the Procurement of Goods and Services", "Article 43 After the end of the bidding deadline, less than three bidders participate in the bidding, except for the cancellation of the procurement task, the bidding and procurement unit shall report to the people's financial departments of cities divided into districts and autonomous prefectures, and the financial departments shall deal with them in accordance with the following principles:
A) the bidding documents do not have unreasonable terms, the time and procedures of the tender announcement comply with the provisions, agree to adopt competitive negotiation, inquiry or a single way of procurement;
B) there are unreasonable terms in the bidding documents, the time and procedures of the tender announcement do not meet the requirements, the bid shall be scrapped, and the bidding and procurement unit shall be instructed to re-bid in accordance with the law. During the bid evaluation period, if there are less than three first-class merchants who meet the professional conditions or respond substantively to the bidding documents, they may be implemented in accordance with the provisions of the preceding paragraph. ”
-
1. According to the ** Procurement Law of the People's Republic of China, "Article 30 Goods or services that meet one of the following circumstances may be procured through competitive negotiation in accordance with this Law: (1) There is no first-class bidding or no qualified subject matter after the bidding, or the re-bidding fails to be established; (2) The technology is complex or special in nature, and the detailed specifications or specific requirements cannot be determined; C) the time required to adopt the bidding can not meet the urgent needs of users; (4) The total amount of the town cannot be calculated in advance. ”
"Procurement can therefore be carried out on the basis of competitive negotiations.
2. According to the "Administrative Measures for Bidding and Bidding for the Procurement of Goods and Services", "Article 43 After the end of the bidding deadline, less than three bidders participate in the bidding, except for the cancellation of the procurement task, the bidding and procurement unit shall report to the people's financial departments of cities divided into districts and autonomous prefectures, and the financial departments shall deal with them in accordance with the following principles: (1) There are no unreasonable terms in the bidding documents, and the time and procedures for the bidding are in accordance with the regulations, and it is agreed to adopt competitive negotiation, inquiry or a single procurement method; B) there are unreasonable terms in the bidding documents, the time and procedures of the tender announcement do not meet the requirements, the bid shall be scrapped, and the bidding and procurement unit shall be instructed to re-bid in accordance with the law. During the bid evaluation period, if there are less than three bidders who meet the professional conditions or respond substantively to the bidding documents, they may be implemented in accordance with the provisions of the preceding paragraph.
Accordingly, competitive negotiation, inquiry or a single way of procurement can be adopted.
-
When a project is scrapped, if you want to conduct a second tender, then you need to go through the relevant laws and regulations. This is a point that everyone is not clear, and the opening of the second bidding needs to go through the following process in order to better handle it. The content of the bidding cannot be identified as duplicated, and it needs to be carried out through relevant legal provisions.
1. What should I do if He Qishi's second bidding is scrapped When a project is scrapped, if you want to conduct a second bidding, then you need to go through the relevant laws and regulations. This is a point that everyone is not clear, and the opening of the second bidding needs to go through the following process in order to better handle it. Second, what is the second bidding When a project is scrapped, if you want to carry out a second bidding, then when a project is scrapped, if you want to carry out a second bidding, then you need to go through the relevant laws and regulations to carry out this is a point that we are not clear, for the second bidding needs to go through the following process to better handle.
3. Requirements of the Bidding Law for the Second Bidding When a project is scrapped, if you want to enter the second bidding, then it needs to be carried out through the relevant legal provisions. This is a point that everyone is not clear, and the opening of the second bidding needs to go through the following process in order to better handle it. Zaibu.
When a grand mal seizure occurs, the first thing is that there is a lot of secretions from the respiratory tract, which can easily cause airway obstruction or aspiration pneumonia. From the beginning of a grand attack, the patient's head should be turned to one side to allow the discharge to flow naturally. In addition, the collar and buttons of the patient's shirt should be unbuttoned to keep the airway open.
Hello: 1. If it is mediated by the people's court in accordance with the law, if the mediation is invalid, it can only be judged in accordance with the law. Because mediation must follow the principle of voluntariness and non-illegality, no person or any unit may force others to accept mediation, or accept mediation opinions that they do not agree with the other party. >>>More
There are three ways to fail, the most important thing is to follow your heart's thoughts. >>>More
The first thing to do is to accept the fact of failure, only then can you calm down and find out the reason for the failure. >>>More
If you want to succeed, it is indispensable to study hard, but you are too demanding of yourself and care too much about success, and in the end you will fail due to excessive tension; As long as we do not suffer from gains and losses, let go of excessive demands on ourselves, care too much about success, pay attention to the process and not overly care about the results, calm and calm, not biased, and enjoy in suffering. Treat the graduate school entrance examination with a normal heart, be good at relaxing your emotions in a tense environment, so that the sympathetic nervous system can quickly recover from the state of overexcitement to the balance of excitement and inhibition, and create the best test-taking mentality. Just as the billiards player Ding Junhui won the crown in the World Billiards Championships, the reporter once asked, "What was your mentality at that time?" >>>More