Hello, 1. First of all, you must go to the development and reform department for filing and registration (you need to prepare a feasibility study report, land use certificate, housing use certificate, etc.).
2. After filing, go to the environmental protection department to apply for the pre-examination opinion of the EIA (the filing approval of the development and reform department, the feasibility study report, the land certificate, the housing use certificate, etc.).
3. Entrust a unit with EIA qualification to prepare an EIA report or report form (determined according to the investment amount, scale, and environmental conditions of the area where your plant is located, and the technical information and environmental drawings of the project need to be provided).
4. Submit the EIA document to the environmental protection department for approval.
5. Application for trial production.
6. Completion of environmental protection acceptance (EIA documents, environmental protection approval).
7. Officially put into production.
This is only the basic procedure that needs to be taken by the environmental protection port, and if it involves the construction of the factory, it is necessary to plan and land and other departments to approve the procedures.
-
1: Painting equipment 2 baking room equipment 3: Instructions for the use of three types of air purification equipment, layout planning drawing, equipment qualification certificate.
If it is difficult to pass, it is necessary to have instructions for the use of water-based paint and a certificate of conformity. No matter how difficult it is to pass, there are spray guns--- micro-spray spray guns and minimally invasive touch-up paint construction processes, which indicate that the amount of paint is very small, and it is a local repair rather than a large-area spray gun. The environmental protection department does not have the equipment to test whether your emissions meet the standards for the time being, but through your equipment and process, you can understand the size and degree of harm of your emissions to judge whether you are qualified.
-
Legal analysis: Entrust a qualified EIA company. Take the project approval documents (or the notice that allows the preliminary work to be carried out) and the feasibility study report to the EIA company, and the EIA company will send someone to your processing site for on-site investigation.
The EIA company prepares the EIA report. The EPA commissioned the review, and after the report came out, it was sent to the EPB for review. The environmental protection bureau approves the revised report and submits it to the local environmental protection bureau, and the environmental protection bureau also has a public announcement, and the approval document will be issued after the publicity, and after the approval document is obtained, the EIA procedures will be completed.
Legal basis: "Law of the People's Republic of China on Environmental Impact Assessment" Article 16 The State implements classified management of the environmental impact assessment of construction projects according to the degree of impact on the environment. The construction unit shall, in accordance with the following provisions, organize the preparation of environmental impact reports, environmental impact report forms or fill in the environmental impact registration form (hereinafter referred to as environmental impact assessment documents):
1) If it may cause a major environmental impact, an environmental impact report shall be prepared and a comprehensive assessment of the resulting environmental impact shall be conducted; (2) If it may cause a slight environmental impact, an environmental impact report form shall be prepared to analyze or make a special assessment of the environmental impact generated; (3) If the environmental impact is very small and no environmental impact assessment is required, the environmental impact registration form shall be filled. The catalogue of classified management of environmental impact assessment of construction projects shall be formulated and published by the competent department of ecology and environment.
-
Whether an EIA is required for a project or not, and whether the EIA is a report or a report form is based on the Ministry of Environmental Protection's "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects".
According to the new "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects" implemented on June 1, 2015, the business area of automobile and motorcycle maintenance sites is 5,000 square meters or more; If you are involved in environmentally sensitive areas, you need to prepare an EIA report form, and the rest only need to fill out a registration form.
There are pictures and truths.
-
In accordance with the "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects", which came into effect on September 1, 2017, Article 5 stipulates that the environmental impact assessment category of cross-industry and compound construction projects shall be determined according to the highest single grade. According to Article 126 of the directory, the automobile repair plant has a business area of 5,000 square meters and above; Involving environmentally sensitive areas need to do a report form, other registration forms, but at the same time the car belongs to general equipment, according to the directory of Article 23 general equipment manufacturing and maintenance, there is electroplating or painting process and annual use of oil-based paint (including thinner) 10 tons and above need to make a report, other such as spray paint but the annual consumption of less than 10 tons (including thinner) of the project should be a report form, only simple assembly is also to fill in the registration form.
Therefore, if you strictly check the list, the car repair shop with spray painting is at least required to make a report form.
-
Refer to the 2017 edition (including appendices) National Economic Industry Classification (GBT4754-2017) 811 Repair and maintenance of automobiles and motorcycles8111 Automobile repair and maintenance refers to the professional repair services of automobile repair shops and roadside stores, including oiling, inflation, waxing, polishing, painting, cleaning, replacement of spare parts, ** parts and other services for automobiles, excluding the activities of dismantling, modification and overhaul of automobiles.
Automobile repair stations include painting links, and combined with the Ministry of Environmental Protection's "Catalogue of Classified Management of Environmental Impact Assessment of Construction Projects", automobile repair shops should apply for an environmental impact registration form.
The social responsibility audit includes the following main contents: >>>More
The traditional sheet metal painting process generally requires the following processes. >>>More
Working procedures for environmental impact assessment.
1. Preparation stage. >>>More
Depending on what kind of car it is, there must be a color difference, but the color difference with good paint mixing technology will be relatively small.
An Environmental Impact Assessment (EIA) can be defined as the process of developing environmental consequences for a project. Environmental impact assessment aims to evaluate and express the environmental impact of any available method in the decision-making process and is an important method to ensure the survival of people in environmental conditions. It is to analyze, evaluate and evaluate the environmental impact that may be caused by the implementation of planning and construction projects, put forward countermeasures and measures to prevent or mitigate adverse environmental impacts, and track and monitor methods and systems.