What procedures do you need to go through to install photovoltaic power generation?

Updated on society 2024-07-02
3 answers
  1. Anonymous users2024-02-12

    You can call 95598 for consultation first, and then go to the nearest power supply business hall to apply. If you are using a public area, you need to provide proof of consent from other owners, property owners, and neighborhood committees. After providing the application, the power supply company will send someone to the site to investigate, issue an acceptance plan, and the public will design according to the plan, purchase solar panels, inverters, brackets, cables, etc. from qualified units, install them, and then the power supply company will review them.

    After the audit is passed, the power supply company will send someone to install the metering device, sign the grid-connected contract, and carry out grid-connected commissioning. The procedures that need to be handled for photovoltaic power generation projects are to provide the power supply bureau with the owner's business license, legal person ID card, organization certificate, property right certificate, roof agreement, contract energy management agreement, project overview report and other filing materials, and start construction after obtaining the record approval. Provincial-level energy authorities shall, in accordance with the relevant plans of the 13th Five-Year Plan for the development of renewable energy in the country and the absorption capacity of the local power grid, and in accordance with the requirements of the 2020 wind power and photovoltaic power generation project construction work plan, organize the project construction in a standardized and orderly manner; Strictly implement the requirements for monitoring and early warning, and reasonably arrange the scale of new approved (recorded) projects based on the power grid's absorption capacity.

    Organize wind power and photovoltaic power generation enterprises to fill in and update project information such as approval (filing), start-up, construction, and grid connection on the national renewable energy power generation project information management platform on a monthly basis; Increase coordination with land, environmental protection and other departments, promote the reduction of non-technical costs, and create a good environment for investment in wind power and photovoltaic power generation construction.

    Legal basis: Law of the People's Republic of China on the Promotion of Circular Economy

    Article 3 The development of circular economy is a major strategy for national economic and social development, and should follow the overall planning, reasonable layout, adaptation to local conditions, pay attention to practical results, promote and market guidance, enterprise implementation, and public participation.

  2. Anonymous users2024-02-11

    Individuals only need to go to the local ** for filing to install photovoltaic power generation.

    According to the "Interim Measures for the Management of Distributed Photovoltaic Power Generation Projects in Beijing", distributed photovoltaic power generation projects shall be managed by the district (county) Development and Reform Commission according to the annual scale index of distributed photovoltaic power generation in the region, and exempt from supporting documents such as power generation business permits, planning and site selection, land pre-examination, environmental impact assessment, energy conservation assessment and social risk assessment. Where:

    1. The distributed photovoltaic power generation project declared by the legal entity shall be filed by the district (county) Development and Reform Commission in accordance with the principle of territoriality, and shall be completed within 5 working days;

    2. The distributed photovoltaic power generation project constructed by natural persons using their own legal residences shall be registered by the district (county) power grid enterprise on behalf of the district (county) power grid enterprise in accordance with the principle of territoriality, and shall be completed within 5 working days, and the district (county) power grid enterprise shall report to the district and county development and Reform Commission for filing on a monthly basis.

    Precautions for personal installation of photovoltaic power generation:

    1. The grid-connected voltage of the distributed photovoltaic system is mainly determined by the installed capacity of the system, and the specific grid-connected voltage needs to be determined according to the approval of the access system of the power grid company, and the general household uses AC220V to access the power grid, and the commercial can choose AC380V or 10KV to access the power grid.

    2. The inclination angle of photovoltaic array installation is generally determined by the latitude of the installation site.

    3. Since the main reason affecting photovoltaic power generation is the amount of sunshine, the module should be installed in the direction of the most abundant sunlight, and different installation angles also have an impact on the power generation of photovoltaic modules.

    The above content refers to the official website of the National Energy Administration - Interim Measures for the Management of Distributed Photovoltaic Power Generation Projects in Beijing.

  3. Anonymous users2024-02-10

    Individual applications need to provide the ID card and copy of the handler, household registration book, real estate certificate and other legal supporting documents.

    Hope it helps, thank you.

Related questions
5 answers2024-07-02

Installation quota 12 volume 7 chapter 1 section of the solar power supply part check which quota set, installation quota book 2 electrical equipment installation does not have photovoltaic related quota subheading.

16 answers2024-07-02

Photovoltaic power generation is a technology that directly converts light energy into electrical energy by using the photogenerated volt effect at the semiconductor interface. It is mainly composed of three parts: solar panels (components), controllers and inverters, and the main components are composed of electronic components. Solar cells can be encapsulated and protected in series to form large-area solar cell modules, and then combined with power controllers and other components to form photovoltaic power generation devices. >>>More

17 answers2024-07-02

The procedure is a bit complicated, so it is recommended that you go to a professional for detailed consultation. >>>More

14 answers2024-07-02

Leave of absence.

Organizer: Academic Affairs Office, Academic Affairs Management Office. >>>More

5 answers2024-07-02

1. The location and layout of the chicken farm should meet the animal epidemic prevention standards, and its production area and living area should be separated; 2. The design and construction of the poultry house should meet the requirements of animal epidemic prevention, and the lighting, ventilation, sewage and sewage discharge facilities should be fully arranged; 3. The poultry house should have an isolation enclosure for sick animals, and also prevent the harmless treatment facilities and equipment of sick and dead animals, sewage and sewage; 4. There should be full-time personnel in the poultry house; 5. There should be isolation and disinfection facilities at the entrance and exit of the poultry house; 6. The poultry house should have a sound epidemic prevention system. Later, to carry out large-scale chicken raising, farmers also need to apply for industrial and commercial licenses. Farmers can only sell their chickens to the outside world if they have applied for an industrial and commercial license, otherwise they are illegal.