How long is the quality warranty period for municipal road works

Updated on society 2024-03-28
5 answers
  1. Anonymous users2024-02-07

    The quality warranty period of municipal road engineering is 1 year.

    Article 39 of the Regulations on the Quality Management of Construction Projects stipulates that construction projects shall implement a quality warranty system. When the construction project contractor submits the project completion acceptance report to the construction unit, it shall issue a quality warranty certificate to the construction unit. The warranty certificate, the warranty scope, warranty period and warranty responsibility of the construction project shall be clearly stated.

  2. Anonymous users2024-02-06

    Municipal engineering quality warranty period: the warranty period of urban roads is 1 year; 2 years for the installation of electrical pipelines, water supply and drainage pipes and equipment; The greening shall be handled in accordance with the specific provisions of the contract signed by both parties.

    1. The Regulations on the Administration of Urban Roads (Order No. 198 of June 4, 1996) came into force on October 1, 1996.

    Article 18 Urban roads shall be guaranteed by the project quality system. The urban road warranty period is one year, calculated from the date of delivery. If there is a project quality problem during the warranty period, the relevant responsible unit shall be responsible for the warranty.

    2. The Regulations on the Quality Management of Construction Projects (promulgated by Order No. 279 on January 10, 2000) came into force on January 30, 2000.

    Notes:

    Chapter VI Quality Assurance of Construction Projects.

    Article 39 A quality assurance system shall be implemented for construction projects.

    The contractor of the construction project shall issue a quality assurance certificate to the construction unit when submitting the completion acceptance report to the construction unit. Quality assurance shall clarify the scope, duration and responsibility of the construction project.

    Article 40 Under normal use conditions, the minimum warranty period for construction projects is:

    A) the infrastructure engineering, foundation engineering and main structure engineering of housing construction, according to the design documents specified in the reasonable service life of the project;

    2) Roof waterproofing works, requiring toilets, rooms and external walls to be waterproof and leaking, valid for 5 years;

    c) Heating and cooling system: two heating periods and two cooling periods;

    4) Installation and decoration of electrical pipelines, water supply and drainage pipelines and equipment for 2 years.

    The warranty period for other items shall be agreed between the employer and the contractor.

  3. Anonymous users2024-02-05

    The shelf life of municipal road works is 1 year. According to Article 18 of the Regulations on the Administration of Urban Roads, the quality warranty system for urban roads is implemented.

    The warranty period for urban roads is one year, calculated from the date of delivery. If there is a project quality problem during the warranty period, the relevant responsible unit shall be responsible for the warranty.

    When the construction project contractor submits the project completion acceptance report to the construction unit, it shall issue a quality warranty certificate to the construction of a single hole. The warranty certificate, the warranty scope, warranty period and warranty responsibility of the construction project shall be clearly stated.

  4. Anonymous users2024-02-04

    How long is the quality warranty period of municipal road engineering, the law does not clearly stipulate, municipal road engineering belongs to infrastructure engineering, and the warranty period under normal use conditions should be the reasonable service life of the project specified in the design documents.

    1. Why the quality warranty period is the defect liability period.

    The project warranty period refers to the period during which the contractor bears the warranty responsibility for the project as agreed by the parties in the contract, and is the statutory minimum warranty period under the normal use of the project.

    The defect liability period refers to the period during which the contractor undertakes the obligation to repair the defect in accordance with the contract and the employer withholds the quality deposit.

    As a result, there are significant differences in the nature and function of the engineering warranty period and the defect liability period.

    Second, how to stipulate the warranty period for the construction quality of electric power projects.

    The warranty period for the quality of electric power projects such as sails is generally two years, which requires the employer and the contractor to agree in writing in the construction contract, and at the same time agree on the maintenance matters, the responsibilities of both parties, the amount of the warranty, etc. The prerequisite for the construction party to repair is that the time point of the problem is still within the warranty period and the normal use of the completed project is guaranteed before the accident.

    3. Acceptance specifications and standards for municipal projects.

    The acceptance specifications of municipal engineering mainly include urban road engineering construction and quality acceptance specifications, water supply and drainage pipeline engineering construction and acceptance specifications, urban bridge engineering construction and quality acceptance specifications, concrete structure engineering construction quality acceptance specifications, highway engineering quality inspection and evaluation standards, urban road lighting engineering construction and acceptance procedures, etc. The process, location and unit project of the political road project should be divided according to the following requirements: 1. Process:

    The process is divided into: roadbed, base layer, surface layer, ancillary structures, etc. Second, the location:

    Municipal road engineering should not be divided into parts, but it can also be divided into several parts according to length. 3. Unit project: An independent accounting project in municipal road engineering should be a unit project.

    The same municipal road project that adopts separate accounting in phases should be a number of unit projects.

    Article 39 of the Regulations on the Quality Management of Construction Projects.

    The construction project implements a quality warranty system.

    When the construction project contractor submits the completion acceptance report of the cherry blossom delivery project to the construction unit, it shall issue a quality warranty certificate to the construction unit. The quality warranty shall specify the warranty scope of the construction project, the warranty period and the warranty responsibility of the rubber bush.

    Article 40 of the Regulations on the Quality Management of Construction Projects.

    Under normal use conditions, the minimum warranty period for construction projects is:

    A) infrastructure engineering, housing construction foundation engineering and main structure engineering, for the design documents specified in the reasonable service life of the project;

    2) Roof waterproofing works, toilets with waterproof requirements, rooms and external walls for leakage prevention, for 5 years;

    3) Heating and cooling system, for 2 heating periods and cooling periods;

    4) Electrical pipelines, water supply and drainage pipelines, equipment installation and decoration projects, for 2 years.

    The warranty period for other items shall be agreed between the employer and the contractor.

    The warranty period of the construction project shall be calculated from the date of acceptance of the completion of the project.

  5. Anonymous users2024-02-03

    Legal analysis: the quality warranty period of municipal road engineering is 1 year.

    Legal basis: "Regulations of the People's Republic of China on the Quality Management of Construction Projects" Article 39 The quality warranty system shall be implemented for construction projects. When the construction project contractor submits the project completion acceptance report to the construction unit, it shall issue a quality warranty certificate to the construction unit.

    In the quality warranty letter, the regiment shall clarify the warranty scope, warranty period and warranty responsibility of the construction project.

Related questions
3 answers2024-03-28

Emergency plan, special construction plan 370

Decoration Engineering Special Construction Organization Design 314 >>>More