What are the materials given to the supervision during the construction process of the construction

Updated on society 2024-03-02
5 answers
  1. Anonymous users2024-02-06

    The supervision of the archival documents and the construction unit are different, they will collect their own, even if you give him a copy is useless, the archiving materials must be the original, and like the application form and the inspection form, you have reported during the construction process, he must also have it.

    The following is the Shenyang City supervision document archive information, I don't know which region of Liaoning you are, but they are all the same. My advice to you is to go to the **** archive directory of the urban construction archives in your district and city, which will be more accurate. The best way is to ask the supervisor directly what information we need from the construction unit for them to file.

    Supervision unit archival materials:

    1. Construction organization design (plan) application form.

    2. The project management system is submitted for review.

    3. Application form of the construction unit.

    4. Notice of supervision engineer.

    5. Project completion acceptance application form.

    6. Relevant quality issues in the minutes of the supervision meeting.

    7. Supervision of the quality of the monthly report.

    8. Summary of project completion.

    9. Report form for resumption of work of the project.

    10. Work suspension order.

    11. Construction survey pay-off inspection form.

    12. (Division, unit project) project inspection audit form.

    13. (concealed, intermediate acceptance) project inspection audit form.

    14. (Safety and function inspection, equipment operation and commissioning) engineering inspection audit form 15, nonconforming item disposal records.

    16. Relevant information on the handling of engineering quality accidents.

    17. Documents and materials related to project rewards and punishments.

    18. Quality information feedback processing record of the testing department.

    19. Application form for the final extension of the temporary project.

    20. Temporary final extension approval form for the project.

    21. Project change application form.

    22. Contract disputes, breach of contract reports and handling opinions.

  2. Anonymous users2024-02-05

    Each owner is different.

  3. Anonymous users2024-02-04

    Commencement Submission: Letter of Appointment of the Director and Project Supervision Agency. The first regular meeting of the supervision is submitted:

    Supervision planning, supervision rules. Supervision monthly report: submitted on a monthly basis.

    Supervision notice Contact form: to be submitted when it occurs. Summary of branch project supervision, summary of annual supervision work:

    Submit according to the needs of the project. Progress investment review letter: submit after reviewing the content submitted by the construction unit.

    The project is submitted before the completion of the initial inspection and acceptance.

    Superintendent:

    The word "supervision" can be understood as a noun or as a verb referring to a specific act. The corresponding noun in English is supervision, and the verb is supervise. It can be seen that supervision is a foreign combination of words, which has no clear definition in Chinese dictionaries, and how to fully and accurately explain and understand its meaning needs to be further studied.

    China's construction supervision system is introduced from abroad, among them"Superintendent:"The term is borrowed from the appellation of countries such as Japan.

  4. Anonymous users2024-02-03

    Commencement submission: the letter of appointment of the director and the first regular supervision meeting of the project supervision agency (including copies of enterprises and personnel) shall be submitted: supervision planning, supervision rules (pre-production, such as safety, foundation, etc.).

    The rest of the detailed rules will be submitted before the construction preparation organization along with the progress of the project.

    Supervision monthly report: submitted on a monthly basis.

    Supervision notice Contact form: to be submitted when it occurs.

    Division project supervision summary, annual (half-year) supervision work summary: according to the needs of the project to submit the progress of the investment audit book: review the content submitted by the construction unit and submit it to the regular supervision meeting (including the first time) record: submit it after sorting out the countersign.

    Supervision summary Supervision evaluation report: submitted before completion acceptance after the initial inspection of the completion of the project.

  5. Anonymous users2024-02-02

    1. Survey and design documents, construction project supervision contracts and other contract documents.

    2. Supervision planning and supervision implementation rules.

    3. Design disclosure and drawing review.

    Meeting Minutes. 4. Construction organization design.

    5. Documents and materials for the qualification of the subcontractor.

    2. The management of supervision data should be responsible for the chief engineer, and a special person should be designated for specific implementation.

    3. The supervision data should be sorted out and filed in a timely manner after the supervision work at each stage.

Related questions
10 answers2024-03-02

The constructor is the technical organization and management personnel at the grassroots level. The main work content is to go deep into the construction site under the leadership of the project manager. >>>More

5 answers2024-03-02

Summary. If the migrant worker sues you, the affiliated unit and the affiliated unit will be jointly and severally liable. If you choose workers' compensation, the traffic accident compensation will be exercised by the employer, and if you choose the traffic accident compensation, the employer will not be responsible, I suggest that in this case you had better choose the work-related injury, because the perpetrator of the traffic accident may not have the ability to compensate. >>>More

3 answers2024-03-02

1. The developer Qing Brother is the construction unit, and the builder is the construction unit; >>>More

9 answers2024-03-02

The quality objectives and level of the project are concretized through design supervision, which is used as the basis for construction. The quality of the design directly affects the use value and function of the project, and is the decisive link of the project quality. >>>More

7 answers2024-03-02

The basis for the preparation of the design of the construction organization generally includes the following parts: >>>More